BLOG
04 March 2008
What happened to 2007 network upgrades? Quite a bit of upgrading to
the main network did happen although not complete the final two
wireless links will be converted this month. Almost the whole network
is now running on MikroTik equipment
which provides dynamic routing using OSPF and QoS.
16 February 2008
Work to move the repeater from Mrs Wards garden to a new location in
Lt Cornard is complete, now just have to move people to it.
12 November 2007
A sad day today, Mrs Ward passed away. She was a kind lady with a bright
outlook on life, in the early days of SVW she who had let
us use her house as a repeater site in Lt Cornard without which
our network link into the Internet in Sudbury would not have been
possible.
15 December 2006
It has been a busy year running the network gradually improving reliability
and stability. Our upgrade project is well underway to convert
the main backbone of the network to a new frequency of 5.8GHz.
24 August 2006
With help from an American ISP we now are using Freeradius for PPPoE
authentication, this makes adding new kit / users to the system
easier. Using a RADIUS server will also allow SVW to offer higher
speeds.
11 February 2006
Reestablished link from Clive's house back to the main SVW backbone,
reconnected remaining users (some decided to leave the club at this point)
back onto the network. Using Clive's house as the main Glemsford wPOP
is working very well indeed :)
06 February 2006
The building owner inexplicably switched off power to our main Glemsford repeater without warning! The UPS ran the system for an hour and then our network was off in Glemsford :( Later that day Clive and I managed to reroute most users through his house.
19-20 January 2006
A few of us made our way over to Prague for the first MikroTik (they write the software for our routers) Users Meeting (MUM 2006). We met many like minded people building wireless networks for communities and for profit.
09 July 2005
Replaced radio and antenna at main Glemsford Wireless Point of Presents (wPOP) as it was thought to be causing problems after a thunder storm, also tested for radio spectrum interference. The problem later transpired to be a rouge wireless client.
28 June 2005
Migrated all users onto new Mount Bures high capacity Internet connection.
10 June 2005
Second part of new connection in Mount Bures arrived and began testing that with some real users.
9 April 2005
Connected a new internet connection in Mount Bures and began to test it.
19 February 2005
Finalised network rearrangement for Lamarsh and Henny by installing an extra radio in Lamarsh to connect into the main network at Workhouse Green.
12 February 2005
Began a rearrangement of the Lamarsh and Henny part of the network as the internet connection in Sudbury was being closed down. We had to move from Sudbury as the owners of the house from which it was connected were moving, their neighbors kindly offered to let us connect in their house but due to the distance from the Sudbury telephone exchange which would limit the maximum bandwidth available there it was decided to remove this link altogether.
13 December 2004
Whilst it was not a Friday (it was a Monday) it was unlucky for a leg of the SVW network which included Workhouse Green and Glemsford. A core router on the network had been running continuously for over three months until that morning when a gardener decided to unplug it! He said, and I quote "When I unplugged that lead I did not like the buzzing sound so did not plug it back in", the buzzing sound was the battery powered UPS keeping the system going in spite of the gardener! The UPS will only keep things running for about 20 minutes before it switches off, at that point we noticed the problem and John Quick popped over the road to switch it back on. The system would not work once switch back on.... Three hours was spent that evening installing a replacement router which also had a new wireless circuit in it to stabilize the Glemsford link.
21 August 2004
With the kind permission from Malcolm of the Glemsford Tyre Centre, Clive and Harvey set about installing the first Glemsford repeater site. Installation took a morning of hard work and the result is that the area surrounding the Tyre Centre can now receive Stour Valley Wireless and with the Clive connected up in the afternoon we were very pleased with the day.
17 August 2004
Well it has been a while since any updates have been posted here
so: SVW has been growing very slowly over the past months and much
work has been done on the main network infrastructure.
A few weeks ago further tests were made to link Glemsford (Suffolk)
into the SVW network. To make this we will require a 12Km link which
should be possible in one hop due to fortunate topography. Once
this is established people in Glemsford will be able to share in
the broadband project.
19 January 2004
First user connected from the Twinstead telephone exchange area,
this user also had their phone line DACs and was please to get broadband.
17 January 2004
Network edge PPPoE router installed Workhouse Green.
09 November 2003
New authentication router (PPPoE) installed in Sudbury, This helps
us manage the network and also provide some protection for the network
from abuse.
11 October 2003
Workhouse Green get a repeater installed and working. This was a
straightforward installation that was completed on a beautiful sunny
Saturday afternoon. The first person in Workhouse Green has connected
to the repeater using standard Wi-Fi kit from PC World. We have
also installed uninterruptible power supplies (UPS) at two other
backbone repeater sites, two more to go.
02 September 2003
Repeater site power failure. Went and reset RCD unit and all seems
OK now, we've calculated that it would cost about £450 to
install Uninterruptible Power Supplies (UPS) at each network point
giving use about 1 hour Up-time in the event of power failure. Any
one want to buy these? ;-)
20 August 2003
NETWORK GOES LIVE. ADSL was enabled at the Cornard
site last night, and after a prolonged battle with a piece of network
hardware, Harvey has managed to get the Internet gateway running.
We are obviously now in the testing stages but everything is running
OK.
14 August 2003
Our Internet supplier has confirmed ADSL will be supplied to the
network next Tuesday. This should mean SVW going live at the same
time. Here's hoping...
10 August 2003
Success! In blistering temperatures, the final antenna has been
erected in Sudbury providing the final link to ADSL. The final 'hop
' is thus finished. The ADSL is ordered, and all being well will
be enabled the start of next week. We're very close now...!
03 August 2003
Reworking the first hop from Sudbury as antenna was not 'seeing'
the ADSL uplink house. Very hot work but now have line of sight
to our ADSL connection in Gt Cornard.
 |
| Sudbury and Gt Cornard, Gt Cornard Upper school in foreground |
02 August 2003
User connected to network, this household has been directly connected
to the network backbone, as their house forms part of it!
26 July 2003
John and Harvey have video conversation between John's office in
Lamarsh and a field very near to Sudbury, using wireless backbone
to carry the data.
25 July 2003
John has been looking at some fantastic free piece software that
will greatly simplify the distribution of the network off the main
links we've already put in place: the
LocustWorld Mesh AP. See the documentation
for more details. It really is as easy as plugging it in and you're
on the network! No technical knowledge involved...
22 July 2003
Trigger
level met. Thanks to Harvey who in his somewhat limited spare
time has been running the Broadband4Bures
campaign. Check whether you are able to get the ADSL service here.
The next step is for BT to give a ready for service date, which
optimistically could be around November apparently. As far as we
can see, SVW ploughs on regardless- the Internet link in Sudbury
will always be faster than anything we will get out in the village.
SVW will also be crucial in distributing the link to those who live
more than 3 km from the village and those who want a cheaper alternative
to ADSL enabling their phone line. The secondary goal of SVW remains
the same- to provide a wireless community network enabling fast
data transfer through the village- video phone calls etc. all become
free and easy once it is in place.
11 July 2003
Trigger level for Bures exchange set for activation of ADSL at
150. Interest from a group in Workhouse Green in getting involved
in SVW as they will always be too far from an exchange to get ADSL.
Various options suggested for the final link into Sudbury, all of
which look very possible. We will look into it when we've got some
time!
30 June 2003
Skeleton of network now in place. Network running from Bures to
Lamarsh and up to Gt Cornard. Still some tweaking to do, all of
which is documented. Network accesses Internet
through ISDN in Bures; Internet access throughout the network seems
to be stable, and the equipment seems to be performing well. Still
looking for the final link to Sudbury.
6 June 2003
Problem solved! We now have somebody willing to act as a repeater
1/2 way along the valley. Kit is installed and working well.
Everything until 25 Feb 2003
[John]
The history of the project so far:
See About Us
Last update
Thursday, March 6, 2008 9:33 PM
|